prince2-closure-pack

Prepare PRINCE2 Closing a Project material: product acceptance, end project report, lessons report, benefits review plan, handover, follow-on actions, and closure recommendation.

SKILL.md

GitHub

PRINCE2 Closure Pack

For detailed management product definitions, read ../../references/prince2-management-products.md when the user needs a complete PRINCE2 document set or asks what each artifact is for.

Use this workflow when the project is ready for planned or premature closure.

Inputs To Ask For

  • Project initiation documentation
  • Latest business case
  • Product acceptance evidence
  • Product status
  • Open risks, issues, and changes
  • Benefits evidence and measurement plan
  • Lessons log
  • Handover requirements

Output Structure

1. Closure Recommendation

  • Close as planned, close with exceptions, or close prematurely
  • Rationale
  • Conditions before closure

2. Product Acceptance

  • Final product
  • Acceptance criteria
  • Acceptance evidence
  • Approver
  • Outstanding defects or limitations

3. End Project Report

  • Original objectives
  • Final result
  • Performance against targets and tolerances
  • Benefits achieved or expected
  • Unresolved risks and issues
  • Follow-on action recommendations

4. Lessons Report

  • What worked
  • What did not work
  • Root causes
  • Recommendations for future projects
  • Evidence or examples

5. Benefits Review Plan

  • Benefits to measure after closure
  • Owner
  • Metric
  • Baseline
  • Review date
  • Data source

6. Handover And Closeout

  • Operational owner
  • Support model
  • Documentation location
  • Contracts or suppliers
  • Archived records
  • Project team release

Quality Bar

  • Closure must confirm acceptance or clearly state why acceptance is incomplete.
  • Benefits do not need to be fully realized at closure, but ownership must be clear.
  • Follow-on actions should have owners.
  • Premature closure still needs evidence, lessons, and handover decisions.