critical-path-analyzer
Analyze construction schedule critical path. Identify critical activities, calculate float, simulate schedule impacts, and optimize project duration.
Files3
View on GitHubSKILL.md3_DDC_Insights/Schedule-Optimization/critical-path-analyzer/SKILL.md
GitHubCritical Path Analyzer
Overview
Analyze construction schedules using Critical Path Method (CPM). Identify critical activities, calculate total and free float, simulate what-if scenarios, and find opportunities to compress schedule.
"Understanding the critical path is essential for effective schedule management" — DDC Community
CPM Concepts
┌─────────────────────────────────────────────────────────────────┐
│ CRITICAL PATH METHOD │
├─────────────────────────────────────────────────────────────────┤
│ │
│ Activity A (5d) ──→ Activity C (10d) ──→ Activity E (3d) │
│ ↓ ↑ │
│ Activity B (8d) ──────────→ Activity D (6d) ───┘ │
│ │
│ Critical Path: A → C → E (18 days) │
│ Float on B→D: 4 days │
│ │
└─────────────────────────────────────────────────────────────────┘
Technical Implementation
from dataclasses import dataclass, field
from typing import List, Dict, Optional, Set, Tuple
from datetime import datetime, timedelta
from collections import defaultdict
import heapq
@dataclass
class Activity:
id: str
name: str
duration: int # days
predecessors: List[str] = field(default_factory=list)
successors: List[str] = field(default_factory=list)
# Calculated values
early_start: int = 0
early_finish: int = 0
late_start: int = 0
late_finish: int = 0
total_float: int = 0
free_float: int = 0
is_critical: bool = False
# Optional attributes
resources: List[str] = field(default_factory=list)
cost: float = 0.0
actual_start: Optional[datetime] = None
actual_finish: Optional[datetime] = None
percent_complete: float = 0.0
@dataclass
class ScheduleAnalysis:
project_duration: int
critical_path: List[str]
critical_activities: List[Activity]
near_critical_activities: List[Activity] # Float <= threshold
total_activities: int
float_distribution: Dict[int, int]
class CriticalPathAnalyzer:
"""Analyze construction schedule critical path."""
def __init__(self):
self.activities: Dict[str, Activity] = {}
self.analysis: Optional[ScheduleAnalysis] = None
def add_activity(self, id: str, name: str, duration: int,
predecessors: List[str] = None,
resources: List[str] = None,
cost: float = 0.0) -> Activity:
"""Add activity to schedule."""
activity = Activity(
id=id,
name=name,
duration=duration,
predecessors=predecessors or [],
resources=resources or [],
cost=cost
)
self.activities[id] = activity
# Update successor relationships
for pred_id in activity.predecessors:
if pred_id in self.activities:
self.activities[pred_id].successors.append(id)
return activity
def import_schedule(self, activities: List[Dict]) -> int:
"""Import activities from list of dicts."""
count = 0
for act in activities:
self.add_activity(
id=act['id'],
name=act['name'],
duration=act['duration'],
predecessors=act.get('predecessors', []),
resources=act.get('resources', []),
cost=act.get('cost', 0)
)
count += 1
return count
def calculate_critical_path(self, near_critical_threshold: int = 5) -> ScheduleAnalysis:
"""Calculate critical path using forward and backward pass."""
if not self.activities:
raise ValueError("No activities to analyze")
# Reset calculations
for act in self.activities.values():
act.early_start = 0
act.early_finish = 0
act.late_start = 0
act.late_finish = 0
act.total_float = 0
act.free_float = 0
act.is_critical = False
# Forward pass - calculate early start/finish
self._forward_pass()
# Determine project duration
project_duration = max(act.early_finish for act in self.activities.values())
# Backward pass - calculate late start/finish
self._backward_pass(project_duration)
# Calculate float and identify critical activities
critical_path = []
critical_activities = []
near_critical = []
for act in self.activities.values():
act.total_float = act.late_start - act.early_start
# Calculate free float
if act.successors:
min_succ_es = min(self.activities[s].early_start for s in act.successors)
act.free_float = min_succ_es - act.early_finish
else:
act.free_float = project_duration - act.early_finish
# Identify critical (zero float)
if act.total_float == 0:
act.is_critical = True
critical_activities.append(act)
elif act.total_float <= near_critical_threshold:
near_critical.append(act)
# Build critical path sequence
critical_path = self._build_critical_path_sequence(critical_activities)
# Float distribution
float_dist = defaultdict(int)
for act in self.activities.values():
float_dist[act.total_float] += 1
self.analysis = ScheduleAnalysis(
project_duration=project_duration,
critical_path=critical_path,
critical_activities=critical_activities,
near_critical_activities=near_critical,
total_activities=len(self.activities),
float_distribution=dict(float_dist)
)
return self.analysis
def _forward_pass(self):
"""Forward pass to calculate early start/finish."""
# Topological sort
in_degree = {act_id: len(act.predecessors) for act_id, act in self.activities.items()}
queue = [act_id for act_id, degree in in_degree.items() if degree == 0]
while queue:
act_id = queue.pop(0)
act = self.activities[act_id]
# Early start is max of predecessor early finishes
if act.predecessors:
act.early_start = max(
self.activities[pred].early_finish for pred in act.predecessors
)
else:
act.early_start = 0
act.early_finish = act.early_start + act.duration
# Process successors
for succ_id in act.successors:
in_degree[succ_id] -= 1
if in_degree[succ_id] == 0:
queue.append(succ_id)
def _backward_pass(self, project_duration: int):
"""Backward pass to calculate late start/finish."""
# Start from end activities
end_activities = [act for act in self.activities.values() if not act.successors]
for act in end_activities:
act.late_finish = project_duration
act.late_start = act.late_finish - act.duration
# Process in reverse topological order
processed = set(act.id for act in end_activities)
queue = list(end_activities)
while queue:
act = queue.pop(0)
for pred_id in act.predecessors:
pred = self.activities[pred_id]
# Late finish is min of successor late starts
new_late_finish = act.late_start
if pred.late_finish == 0 or new_late_finish < pred.late_finish:
pred.late_finish = new_late_finish
pred.late_start = pred.late_finish - pred.duration
# Check if all successors processed
all_succ_processed = all(
s in processed for s in pred.successors
)
if all_succ_processed and pred_id not in processed:
processed.add(pred_id)
queue.append(pred)
def _build_critical_path_sequence(self, critical_activities: List[Activity]) -> List[str]:
"""Build ordered critical path sequence."""
if not critical_activities:
return []
# Find start of critical path (no critical predecessors)
critical_ids = {act.id for act in critical_activities}
start_acts = [act for act in critical_activities
if not any(p in critical_ids for p in act.predecessors)]
if not start_acts:
return [act.id for act in critical_activities]
# Build sequence
path = []
current = start_acts[0]
while current:
path.append(current.id)
# Find next critical successor
critical_successors = [s for s in current.successors if s in critical_ids]
current = self.activities[critical_successors[0]] if critical_successors else None
return path
def simulate_delay(self, activity_id: str, delay_days: int) -> Dict:
"""Simulate impact of delay on an activity."""
if activity_id not in self.activities:
raise ValueError(f"Activity {activity_id} not found")
activity = self.activities[activity_id]
original_duration = activity.duration
# Temporarily modify duration
activity.duration = original_duration + delay_days
# Recalculate
new_analysis = self.calculate_critical_path()
# Restore original
activity.duration = original_duration
original_analysis = self.calculate_critical_path()
impact = {
"activity": activity_id,
"delay_days": delay_days,
"original_duration": self.analysis.project_duration,
"new_duration": new_analysis.project_duration,
"project_impact": new_analysis.project_duration - original_analysis.project_duration,
"absorbed_by_float": delay_days <= activity.total_float,
"new_critical_path": new_analysis.critical_path,
"critical_path_changed": new_analysis.critical_path != original_analysis.critical_path
}
return impact
def find_compression_opportunities(self, target_reduction: int) -> List[Dict]:
"""Find activities that could be crashed to reduce duration."""
if not self.analysis:
self.calculate_critical_path()
opportunities = []
for act in self.analysis.critical_activities:
# Assume activities can be crashed by 20% max
max_crash = int(act.duration * 0.2)
if max_crash > 0:
opportunities.append({
"activity_id": act.id,
"activity_name": act.name,
"current_duration": act.duration,
"max_crash_days": max_crash,
"crash_cost_per_day": act.cost * 0.5 / max_crash if max_crash else 0,
"on_critical_path": True
})
# Sort by crash cost
opportunities.sort(key=lambda x: x["crash_cost_per_day"])
return opportunities
def get_float_report(self) -> str:
"""Generate float analysis report."""
if not self.analysis:
self.calculate_critical_path()
lines = [
"# Float Analysis Report",
"",
f"**Project Duration:** {self.analysis.project_duration} days",
f"**Critical Activities:** {len(self.analysis.critical_activities)}",
f"**Near-Critical Activities:** {len(self.analysis.near_critical_activities)}",
"",
"## Critical Path",
"",
" → ".join(self.analysis.critical_path),
"",
"## Activities by Float",
"",
"| Activity | Duration | ES | EF | LS | LF | TF | FF | Critical |",
"|----------|----------|----|----|----|----|----|----|----------|"
]
# Sort by float
sorted_acts = sorted(self.activities.values(), key=lambda a: a.total_float)
for act in sorted_acts:
crit = "YES" if act.is_critical else ""
lines.append(
f"| {act.id} | {act.duration} | {act.early_start} | {act.early_finish} | "
f"{act.late_start} | {act.late_finish} | {act.total_float} | {act.free_float} | {crit} |"
)
return "\n".join(lines)
def generate_gantt_data(self, start_date: datetime) -> List[Dict]:
"""Generate data for Gantt chart visualization."""
gantt_data = []
for act in self.activities.values():
gantt_data.append({
"id": act.id,
"name": act.name,
"start": (start_date + timedelta(days=act.early_start)).isoformat(),
"end": (start_date + timedelta(days=act.early_finish)).isoformat(),
"duration": act.duration,
"float": act.total_float,
"is_critical": act.is_critical,
"predecessors": act.predecessors,
"progress": act.percent_complete
})
return gantt_data
Quick Start
# Initialize analyzer
analyzer = CriticalPathAnalyzer()
# Add activities
analyzer.add_activity("A", "Site Prep", 5)
analyzer.add_activity("B", "Foundation Excavation", 8, predecessors=["A"])
analyzer.add_activity("C", "Foundation Forms", 4, predecessors=["B"])
analyzer.add_activity("D", "Foundation Pour", 2, predecessors=["C"])
analyzer.add_activity("E", "Foundation Cure", 7, predecessors=["D"])
analyzer.add_activity("F", "Steel Erection", 15, predecessors=["E"])
analyzer.add_activity("G", "MEP Rough-in", 20, predecessors=["F"])
analyzer.add_activity("H", "Exterior Envelope", 25, predecessors=["F"])
analyzer.add_activity("I", "Interior Finishes", 30, predecessors=["G", "H"])
analyzer.add_activity("J", "Final Inspection", 3, predecessors=["I"])
# Calculate critical path
analysis = analyzer.calculate_critical_path()
print(f"Project Duration: {analysis.project_duration} days")
print(f"Critical Path: {' → '.join(analysis.critical_path)}")
print(f"Critical Activities: {len(analysis.critical_activities)}")
# Simulate delay
impact = analyzer.simulate_delay("F", 5)
print(f"\nDelay Impact: {impact['project_impact']} days")
print(f"Absorbed by Float: {impact['absorbed_by_float']}")
# Find compression opportunities
opportunities = analyzer.find_compression_opportunities(10)
for opp in opportunities[:3]:
print(f"Crash {opp['activity_name']}: up to {opp['max_crash_days']} days")
# Generate report
print(analyzer.get_float_report())
Requirements
pip install (no external dependencies)